in a poor state of repair, as well as the railway yard that serves   Technical assistance for the development and implementati-
               the C-1 San Sebastián and Media Distancia Irún/Vitoria lines.  on of a unified control centre for ertms (ccue) and adaptation
               The project includes, on the one hand, architectural integra-  of existing facilities and equipment on high-speed lines in the
               tion into the environment, compliance with accessibility pa-  north-west region
               rameters, improvement of pedestrian flows and integration of   The objective of this project is to unify and standardize the
               the current track.                               ERTMS control centers on all high-speed lines in the north-  guía de empresas
               It also includes the replacement of the current level crossing   west region, including the continuity and automation of the
               between the side platform and the central platform, which se-  process of applying temporary speed restrictions.
               parates the main tracks 1 and 2 from the other 13 tracks, with   This will improve not only the operation of ERTMS, but also its
               a pedestrian walkway.                            maintenance, as real-time information on the status of operati-
               The central platform will be rebuilt and its dimensions will be   ons will be available at local and backup centers on all lines.
               extended to a length of 120 meters in order to comply with   Consultrans is the expert consultancy that Adif has entrusted
               current regulations. As far as the action on the tracks is con-  with ensuring that this project is carried out in accordance
               cerned, it will be necessary to eliminate the current track 3 to   with the requirements of reliability, availability, maintaina-
               accommodate the extension of the platform and to remodel   bility and safety (RAMS and Regulation 402), as well as the
               track 5, while maintaining its functionality.    highest levels of cybersecurity and interoperability, through
               The project will be designed using BIM methodology, inclu-  - Installation of the new equipment.
               ding 3D and 4D models of the planned works.       - Detailed  engineering  for the  specification,  design,  deve-
                                                                  lopment and configuration of the ERTMS Unified Control
               Technical assistance for the control and supervision of the   Center (CCUE), as well as the performance of functional
               construction project works on the safety installations affec-  validation tests and the verification of the installations in
               ted by the implementation of the 4+4+2 scheme at atocha   each of the provisional and definitive situations.
               cercanías station                                 - Adaptation of the current maintenance processes (Service
               The objective of this project is to modify the signaling and   Level Agreements - SLAs, penalties and KPIs).
               telecommunications installations affected by the track works   - Planning of training activities aimed at training Adif/Adif AV
               to be carried out at Atocha Cercanías station, focusing speci-  staff in the use and operation of the new ERTMS Unified
               fically on the impact on the safety installations resulting from   Control Center.
               the implementation of the 4+4+2 track scheme.
               The current track 8C at Atocha Cercanías will be made   Technical assistance for the control and supervision of the
               available for the parking of trains coming from or going to   execution of the works for the provision of automatic blok-
               the Sol Tunnel (Atocha - Sol - Nuevos Ministerios - Cha-  king devices for the dual carriage of the r3 line of the bar-
               martín), used by the C-3 and C-4 lines of Cercanías de Ma-  celona suburban railway on the parets del vallés - la garriga
               drid, as well as some Media and Larga Distancia services   The objective of the project is to equip the Parets del Vallès-
               of Renfe Operadora. It also includes the transformation of   La Garriga section of the Barcelona R3 suburban railway line
               the current track 10C for the use of the regular services of   with the Automatic Blocking System (ABS), and adapt it to the
               line C-5 (Móstoles-El Soto - Atocha - Fuenlabrada - Hu-  planned doubling of the line.
               manes), eliminating its status as a siding, as well as modi-  It includes the modification of the existing electronic interlok-
               fications to the existing points tracks at the southern end   kings, the installation of new LED signals, the complete rene-
               of the station.                                  wal of the track circuits with audio frequency technology and
               The signaling works will consist of the modification of the   ASFA digital equipment.
               field elements, as well as the adaptation of the existing interior   It also includes the adaptation of telecommunications systems
               equipment in the cab and the necessary modifications to the   through new permanent fiber optic lines, IP equipment, and the
               ENCE, PLO and CTC. These works will be carried out in coor-  integration of video surveillance and object detection systems.
               dination with the track project.                 This project is part of the track doubling works aimed at
               The technical assistance work will ensure that the works are   improving the capacity and efficiency of the rail service
               carried out in accordance with current quality, safety and   on this important regional link. The geographical location
               environmental regulations. It will also include the review of   of the section, in the province of Barcelona, Catalonia,
               technical documents, quality control, supervision of the dif-  is key to the development of the railway infrastructure in
               ferent phases of construction and, finally, the commissioning   the area, allowing for a greater frequency and quality of
               and handover of the facilities to the corresponding mainte-  passenger transport.
               nance department.